Yellow Door Storage is a massive 120,000 sqft. climate-controlled facility rising near the Dotter Rd corridor. This $10M development marks a high-spec shift in Celina’s storage market, offering premium security and advanced HVAC systems. Currently in the early site-prep and utility phase following its April 2026 groundbreaking, the multi-story complex is a key anchor in the area’s southern industrial growth. Expect the official grand opening target of Spring 2027.
Latest Update: Site Planning (Verified: 04/02/2026)
February 2026 – TDLR Permit Registered
April 2026 – Target Site Mobilization
May 2026 – Target Grading & Earthwork
June 2026 – Target Foundation Slab
September 2026 – Target Vertical Framing
Q2 2027 – Target Grand Opening